Jokeri Light Rail contact lines installed in March
Construction of the Jokeri Light Rail system is nearing completion in Otaniemi. Currently on winter break, work will resume in March with installation of contact lines between Maarintie and Otaniementie.
Work this week (Week 9) begins with snow removal. Contact line installations will start during Week 10 and include setting electrical cross-arms and stringing overhead cables. Construction will occur on day shifts and on night shifts, depending on the work phase. Caution should be exercised when near the work area as heavy machinery and equipment will be moving along the tracks from Maarintie all the way to Otaniementie. The work will not result in significant noise.
The contact line work is scheduled to last until Week 13.
Additional information
Text: Jokeri Light Rail
Read more news
New restaurant operator to open at A Blanc after renovation – Täffä Lunch moving into the centre
Three adjacent retail spaces in shopping centre A Blanc will be combined into a single restaurant with 150 customer seats, where Täffä Lunch will open in the autumn.
Aalto offering free education to architects after €260 000 donation
Koulutuksen tavoitteena on täydentää erityisesti arkkitehtialan ammattilaisten osaamista vastaamaan nykypäivän tarpeita.
Unplanned network outage in Aalto network on 15 June from 10:40 to 10:50
Network now working normally